OFFICE OF CHILDREN AND FAMILY SERVICES

 

AGENCY LEVEL

PEF LABOR/MANAGEMENT

MEETING

March 27, 2009

Agenda

 

 

 

 Labor:                                                   Management:

 

Jim Hair                                                                                 Mary Duprey

Janet Ludwig                                                                      Kathleen Economides

Bernard Johnson                                                               Anthony Hough

Dan Leffingwell                                                                   Raymond LaMarco

Sharon Merulla                                                                   Debye Lurie

Susan Mitnick                                                                     Ines Nieves

William Nolan                                                                      John Ouimet

Gwen Pope                                                                          Jeannie Priest

Migdalia Ramos-Ensslin                                                  Barbara Ruff

Eileen Rice

Josephine Rice

Margaret Rice-Harvey

John Ruiz

 

 

 

 

 

 

 

 

 

 

 

OCFS AGENCY LEVEL

PEF LABOR/MANAGEMENT

March 27, 2009

Agenda

 

New Business:

 

1.      Release Protocols

2.      AWOLS – Returns/Revocations

3.      Trauma Intervention Committee

4.      Provisional Appointments

 

Old Business:

 

1.         Recidivism Study

2.         Mandatory Overtime for Nurses

3.            Contract Staff

4.            Mental Health Services

5.         DOJ Update

6.         Facility Closures and Rightsizings

7.         Hazardous Duty Pay

8.         Background Checks for Temporary and Per Diem Hires

9.         EBCI

10.       OCFS Restraint Policy and Procedures

11.       Budget Update

12.       Workplace Violence

 

Reports:

 

1.         Sub-Committee Reports

 

Information:

 

1.         Local Labor Management

2.         Office Moves

3.            Succession Planning

4.            Education Titles and Nurse Recruitment

5.         Communication/Technology/Cell Phones for R.O.

6.         Community Service Teams

7.          Reasonable Accommodations

8.         Agency Labor/Management

9.          Capacity Reports

 

 

 

3/09

 

 

                                          

      OCFS AGENCY LEVEL

PEF LABOR/MANAGEMENT

 

ISSUE:  Release Protocols         

 

 

NEW BUSINESS:                                                    NUMBER      1         

 

OLD BUSINESS:                                                     NUMBER                      

 

COMMITTEE REPORTS:                                       NUMBER                 

 

INFORMATION:                                                       NUMBER ________

 

INITIATED BY:                                                          [X] LABOR  [   ]  MANAGEMENT

 

CONCERNS OF INITIATING PARTY: PEF requests information and discussion:

  1. Copy and explanation of the current release protocol.

a) Timeline memo

           b) Criteria for release and rationale for any changes.

 

DISCUSSION:  The August 12th memo outlined the Standard Release Procedures.  PEF asked if Prescriptive Programming was going to continue and how violent kids were to be handled. Management stated that the behavioral component is not a good measure for recidivism and they do not have a better system to date to replace it.  What is best for the child is looked at, and recommendations are made by the treatment team. Residents are reviewed every 30 days so they don’t linger in the system.

PEF is concerned about the release protocol and asks for further discussion away from the L/M table to look at numbers and effectiveness.

 

RESPONSE:

 

DJJOY distributed August 12, 2008 memo on Standard Release Procedures.

 

 

 

 

 

 

 

 

 

 

3/09

                                        

 

 

 

                                              OCFS AGENCY LEVEL

PEF LABOR/MANAGEMENT

 

ISSUE:  AWOLS     

 

 

NEW BUSINESS:                                                    NUMBER      2         

 

OLD BUSINESS:                                                     NUMBER      ______      

 

COMMITTEE REPORTS:                                       NUMBER                 

 

INFORMATION:                                                       NUMBER ________

 

INITIATED BY:                                                          [X] LABOR  [   ]  MANAGEMENT

 

CONCERNS OF INITIATING PARTY: PEF requests information and discussion regarding the following:

  1. Number of returns and revocations from OCFS facilities for 2008.
  2. Number of youth returning from voluntary agencies and OCFS facilities for 2008.
  3. Statistics for AWOLS for 2007 and 2008, including:

a)    Number of youth from privates and OCFS facilities.

b)    Length of time AWOL

c)    Procedures for dealing with AWOL youth from both private and OCFS facilities.

           d)  Number of OCFS youth currently returned to detention/local jails.

 

DISCUSSION:  

Management wanted to table this discussion until after the FOIL request was responded to. PEF responded that a request should not preclude Management from information sharing.  Management didn’t feel that a fair discussion could take place at this time.

 

 

RESPONSE:

 

This information was previously foiled by PEF.  This agenda item is tabled until next meeting.

 

 

 

3/09

 

 

      OCFS AGENCY LEVEL

PEF LABOR/MANAGEMENT

 

ISSUE:  Therapeutic Intervention Committee           

 

 

NEW BUSINESS:                                                    NUMBER      3         

 

OLD BUSINESS:                                                     NUMBER                      

 

COMMITTEE REPORTS:                                       NUMBER                 

 

INFORMATION:                                                       NUMBER ________

 

INITIATED BY:                                                          [X] LABOR  [   ]  MANAGEMENT

 

CONCERNS OF INITIATING PARTY: PEF requests information and discussion regarding:

  1. A description and explanation of the purpose of this committee.
  2. How is the information gathered being reported and used?
  3. Copies of reports generated to date.

 

DISCUSSION:  

Its purpose if to identify and implement strategies to reduce the number of restraints. PEF questioned the effectiveness when cameras are stationary with no audio. This forum is NOT for disciplining employees.

 

RESPONSE:

Tony Hough will provide the composition of TIC to PEF.

 

 

 

 

 

 

 

 

 

 

3/09

              

  

                            

                            OCFS AGENCY LEVEL

PEF LABOR/MANAGEMENT

 

ISSUE:  Provisional Appointments

 

 

NEW BUSINESS:                                                    NUMBER        4       

 

OLD BUSINESS:                                                     NUMBER                      

 

COMMITTEE REPORTS:                                       NUMBER                 

 

INFORMATION:                                                       NUMBER ________

 

INITIATED BY:                                                          [X] LABOR  [  ]  MANAGEMENT

 

 

CONCERNS OF INITIATING PARTY:  PEF requests information regarding:

1.    Number of staff currently in provisional titles, title and location.

2.    Number of staff that have exceeded the 9-month time frame for provisional appointment.

3.    Has OCFS requested Civil Service schedule exams for specific titles?

4.    Time frames, dates, and list of exams that have been scheduled.

5.    Any info specifically related to Workforce Programs Specialists series.

 

 

DISCUSSION:

List was handed out however – Management could not tell how many had served more than nine months. A variety of titles were discussed in regards to testing.  The Children and Family Services specialist exam has been discussed with Civil Service.  The Youth Counselor exam has been discussed with Civil Service but they are holding back because the State Education Department might change the Specs for this title.. As things change Management will look at different titles and consolidating titles, Which is what Civil Service is doing, to give more lateral and upward mobility, and test more quickly.  This is not a priority at this time.

 

RESPONSE:

 

Personnel provided a handout identifying provisional items.

A list of people who have exceeded the nine month time frame will be provided at the next L/M meeting.

 

 

 

3/09                                       

 

 

                                           OCFS AGENCY LEVEL

PEF LABOR/MANAGEMENT

 

ISSUE:           Recidivism Study

 

 

NEW BUSINESS:                                                    NUMBER                 

 

OLD BUSINESS:                                                     NUMBER         1          

 

COMMITTEE REPORTS:                                       NUMBER                 

 

INFORMATION:                                                       NUMBER ________

 

INITIATED BY:                                                          [X] LABOR  [   ]  MANAGEMENT

 

 

CONCERNS OF INITIATING PARTY: The SFY 2008-09 budget provided $250,000 for OCFS to contract with an external research organization for a study of juvenile recidivism and the effectiveness of residential and community based juvenile justice services in State operated and not-for-profit agencies.

  1. What is the status of the contract?
  2. Has the research begun?  If not, when will it begin, and if it has – the status to date.

      4. Have there been any recidivism studies done since the nineties?  If yes, by

          who, when, and please provide any documentation related to this topic.

 

 

DISCUSSION:  

Management envisioned a three year study, but that seems unlikely. The contractor is  the Vera Institute of Justice.

There is no current study of recidivism data for reconviction..

 

RESPONSE:

 

Funding is still available in current year.  The hope is that it will be refunded for the next.  $250,000 is the total amount.

 

No other research studies are planned for the future.

 

 

3/09

                                       

                                              OCFS AGENCY LEVEL

PEF LABOR/MANAGEMENT

 

ISSUE:   Mandatory Overtime for Nurses

 

 

NEW BUSINESS:                                                    NUMBER                 

 

OLD BUSINESS:                                                     NUMBER        2            

 

COMMITTEE REPORTS:                                       NUMBER                 

 

INFORMATION:                                                       NUMBER ________

 

INITIATED BY:                                                          [X] LABOR  [  ]  MANAGEMENT

 

 

CONCERNS OF INITIATING PARTY:  PEF requests an update on the following:

  1. Implementation of legislation that restricts mandatory overtime.

 

 

DISCUSSION:  

The Legislation provides for exemptions in emergency situations. PEF - OMH has a pilot program in place that seems to be successful. Management – We need to focus on increasing staffing levels and recruiting nurses.

 

 

RESPONSE:

 

DOL putting together formal guidelines which will be based upon the interpretation as to what constitutes an emergency.

Hourly nurse positions have been available at those locations with higher amounts of OT.

     

 

 

 

 

 

 

 

 

 

3/09

                  

 

 

                                OCFS AGENCY LEVEL

PEF LABOR/MANAGEMENT

 

ISSUE:   Contract Staff

 

 

NEW BUSINESS:                                                    NUMBER                 

 

OLD BUSINESS:                                                     NUMBER         3          

 

COMMITTEE REPORTS:                                       NUMBER                 

 

INFORMATION:                                                       NUMBER ________

 

INITIATED BY:                                                          [X] LABOR  [   ]  MANAGEMENT

 

 

CONCERNS OF INITIATING PARTY:  PEF requests information on the following:

  1. Number of contract staff.
  2. Types of services and locations.
  3. Number of consultant contracts and annual costs.
  4. Status of retirees returning for temporary employment including the number, title, location, and time frames.

 

DISCUSSION:

 

13 retirees have returned.1 Ed Coordinator, 1 LMSW, 2 supervising Administrative Analysts, 2 psychiatrists and 3 CSEA titles

 

 

 

RESPONSE:

                                       

Number of TEA’s has been dramatically reduced.

 

Retiree’s list didn’t differentiate between 211 & 212.  Management will forward additional information regarding the number of consultant contracts and the annual costs.

 3/09                                        

 

                                       

 

 

                                         OCFS AGENCY LEVEL

PEF LABOR/MANAGEMENT

 

 

ISSUE:           Mental Health Services

 

 

 

NEW BUSINESS:                                                    NUMBER                 

 

OLD BUSINESS:                                                     NUMBER      _4           

 

COMMITTEE REPORTS:                                       NUMBER                 

 

INFORMATION:                                                       NUMBER ________

 

INITIATED BY:                                                          [X] LABOR [  ]  MANAGEMENT

 

CONCERNS OF INITIATING PARTY:  PEF requests information regarding the following:

 

  1. Update on any current or future plans for the program.
  2. Update on Mental Health staffing.                                 

      4.  Discharge planning for youth having received mental health services.

 

DISCUSSION:  

Management plans to train ten more teams in DBT. It compliments Sanctuary.

The Agency is permitted to fill all MH positions.

Early release planning does not affect discreet MH units – release is based on clinical assessment. There is an entire protocol for anyone receiving MH services and medications.

 

RESPONSE: 

 

Conducted Dialectical Behavior Training.  More training is expected next year.  PEF has offered to provide funding to assist in this effort

 

There is difficulty hiring Psychologists and Psychiatrists due to salary competition.

 

 

3/09

 

                       OCFS AGENCY LEVEL

PEF LABOR/MANAGEMENT

 

 

ISSUE:           DOJ Update

 

 

 

NEW BUSINESS:                                                    NUMBER                 

 

OLD BUSINESS:                                                     NUMBER      _5           

 

COMMITTEE REPORTS:                                       NUMBER                 

 

INFORMATION:                                                       NUMBER ________

 

INITIATED BY:                                                          [X] LABOR [   ]  MANAGEMENT

 

 

 

CONCERNS OF INITIATING PARTY:  PEF requests information regarding any updates connected with the DOJ visits.

1.      Copy of report if available.

 

DISCUSSION:  

No report yet – but some recommendations were made. Facilities have started doing PBS which is out-come based.  ACA establishes standards – but is based on a corrections model.  To do both requires a tremendous amount of data input and paperwork which takes away from direct care of the youth.  There has been some discussion about removing one.

 

RESPONSE: 

 

No report has been issued by DOJ to date.

 

 

 

 

 

 

 

3/09

 

 

OCFS AGENCY LEVEL

PEF LABOR/MANAGEMENT

                                                           

 

ISSUE:           Facility Closures/Rightsizings

 

 

 

NEW BUSINESS:                                                    NUMBER                 

 

OLD BUSINESS:                                                     NUMBER         6          

 

COMMITTEE REPORTS:                                       NUMBER                 

 

INFORMATION:                                                       NUMBER ________

 

INITIATED BY:                                                          [X] LABOR [   ]  MANAGEMENT

 

CONCERNS OF INITIATING PARTY:  PEF requests the following information:

  1. Any updates concerning closures and/or rightsizing of facilities

Note: PEF would like to maintain the same continuity of information sharing that we have had in the past.

 

 

DISCUSSION:  

Management is waiting for budget approval , but is proceeding with the plan for closures.

PEF is concerned that there are not enough locations and vacant items to absorb the affected personnel.

Ella McQueen will close by June 1, 2009 for renovations.

 

RESPONSE:   

 

Original facilities are still scheduled for closure.

 

 

 

 

 

 

3/09

 

 

 

                                        OCFS AGENCY LEVEL

PEF LABOR/MANAGEMENT

 

ISSUE:           Hazardous Duty Pay                                

 

NEW BUSINESS:                                                    NUMBER                 

 

OLD BUSINESS:                                                     NUMBER          7         

 

COMMITTEE REPORTS:                                       NUMBER                             

 

INFORMATION:                                                  NUMBER ________

 

INITIATED BY:                                                          [X] LABOR [   ]  MANAGEMENT

 

CONCERNS OF INITIATING PARTY:  PEF requests an update regarding the provision of Hazardous Duty pay in light of OMH staff receiving HDP in facilities where our OCFS staff are not. 

 

 

DISCUSSION:.

 

 

 

 

 

RESPONSE:  

 

A committee will be formed by Bernard Johnson and Debye Lurie.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

3/09

 

                       

                       OCFS AGENCY LEVEL

PEF LABOR/MANAGEMENT

 

 

ISSUE:           Background and Health Checks for Temporary and Per-Diem            Hires

 

NEW BUSINESS:                                                    NUMBER                 

 

OLD BUSINESS:                                                     NUMBER      __8___

                                                           

COMMITTEE REPORTS:                                       NUMBER                             

 

INFORMATION:                                                 NUMBER ________

 

INITIATED BY:                                                          [X] LABOR [   ]  MANAGEMENT

 

CONCERNS OF INITIATING PARTY:  PEF requests an update on the following:

  1.  Has OCFS followed up with OGS regarding this issue?
  2. Have there been any changes regarding this issue with new contracts?

 

DISCUSSION:  

Background checks have been added to new contracts.  The contractors now have to have their employees sign and notarize that they have no pending criminal charges and have a SCR check if they have regular and substantial contact with youth.

 

 

 

RESPONSE:

 

PEF was appreciative that Personnel added the attestation form for Temp staff to indicate that they have no prior convictions, or nothing pending at the time of hire.

 

 

 

 

 

3/09

 

                        OCFS AGENCY LEVEL

PEF LABOR/MANAGEMENT

 

ISSUE:           EBCI Briefing

 

NEW BUSINESS:                                                    NUMBER                 

 

OLD BUSINESS:                                                     NUMBER          9         

 

COMMITTEE REPORTS:                                       NUMBER                             

 

INFORMATION:                                                       NUMBER  _______

 

 

INITIATED BY:                                                          [X] LABOR [   ]  MANAGEMENT

 

 

CONCERNS OF INITIATING PARTY:  PEF requests an update on the following:

      1.  What is the actual cost per child given the current contract and current

           utilization?

  1. Is there a plan to act on the MST recommendations that Carrion

Presented to the Governor?

  1. What is the utilization rate of the program as of 3/2/09?

 

DISCUSSION: 

Management: Many are at half capacity. FFT Monroe – 40%, MST NYC 93%, MST Onondaga 60%, MST Oneida 100%, MST Mid-Hudson 70%, MTFC 50%, APT 50%, NAFI 30%, Link City Challenge 107%. The new contracts do not pay for slots that are not filled.

PEF – Part of the contract is based on staff availability for referrals, so there is partial payment for empty slots.

RESPONSE:  

 

There were no updates on the figures presented at the last meeting.

 

DJJOY did provide utilization figures.

 

 

 

 

3/09

 

 

 

                                     OCFS AGENCY LEVEL

PEF LABOR/MANAGEMENT

 

 

ISSUE:           OCFS Restraint Policy and Procedures                     

 

 

NEW BUSINESS:                                                    NUMBER                 

 

OLD BUSINESS:                                                     NUMBER         10        

 

COMMITTEE REPORTS:                                       NUMBER                 

 

INFORMATION:                                                                                                       NUMBER  _______

 

INITIATED BY:                                                          [   ] LABOR  [X]  MANAGEMENT

 

CONCERNS OF INITIATION PARTY   PEF requests updates on the following:

1. Please provide a list of numbers of restraints by facility for 12/08-present.

2. PEF requests an update on the Sanctuary implementation, as well as information regarding measurable outcomes.

 

DISCUSSION: 

Management provided statistics for the first quarter.  Training continues with Sanctuary. PEF requested that the Home Office Sanctuary Committee meeting minutes be added to the L/M minutes.  Ines said she would bring the request back to the committee for a vote.

 

RESPONSE: 

 

T. Hough presented restraint statistics to S Merulla.

Sanctuary surveys indicated good results at Annsville.  Results were not as good at Brentwood. 

DJJOY provided a list of sites where Sanctuary training will begin.

 3/09

 

                     

 

                   

 

                         OCFS AGENCY LEVEL

PEF LABOR/MANAGEMENT

 

 

ISSUE:           Budget Update                  

 

 

NEW BUSINESS:                                                    NUMBER                 

 

OLD BUSINESS:                                                     NUMBER        11         

 

COMMITTEE REPORTS:                                       NUMBER                 

 

INFORMATION:                                                       NUMBER  ________

 

INITIATED BY:                                                          [X] LABOR [   ]  MANAGEMENT

 

 

CONCERNS OF INITIATING PARTY:  PEF requests an update on the following:

  1. The Executive Budget calls for 127 FTE abolitions.  Please identify these positions by negotiating unit and work location.  How will these abolitions be accomplished (attrition, layoffs)?

 

2.    The budget identifies a decrease of 288 FTEs from the adjusted FTE level for SFY 2008-09.   There is a discrepancy in the distribution of the changes in the OCFS workforce.  According to the narrative in the Agency Presentation, the net decrease of 288 FTEs reflects a reduction of 294 FTEs offset by 6 additional FTEs associated with child abuse legislation enacted in 2008.  According to the table of “Projected Levels of Employment by Program”, the 288 FTE reductions reflect the loss of 349 FTEs offset by the addition of 61 FTEs. Please clarify.

 

3.    The appropriations bill shows a $2.9 million increase (1.8%) in Contractual Services. A large increase ($4.4 million, 48.7%) in Contractual Services occurs in the Family and Children’s Services Program.  This contradicts information in the Consulting Service Contract table in the Financial Plan, which shows that OCFS employed an estimated 251 employees under consultant contracts in SFY 2008-09 and will employ the same number of contract employees at the same cost in 2009-10.

 

4.    The budget calls for closures and bed reductions at various facilities and programs, effective June 1.  It is apparent that the budget will not be enacted by March 1.  What is the adjusted target date for these closures?

 

5.    The Early Reporting Centers in Albany, Syracuse and Buffalo are targeted for closure.  How will the services currently provided by these programs be provided in the affected communities? 

 

  1. A SFY 2008-09 $8.8 million Maintenance Undistributed appropriation in the Youth Facilities Program for Evidence-based Community Initiatives is eliminated, however the agency indicates that there is $4.2 million in funding for this program, including $3.6 million in State Operations and $.571 million for the Post Residential Supervision Program.  Please clarify.

 

$250,000 in funding in the Youth Facilities Program for a recidivism study is eliminated. There does not appear to be a re-appropriation for the funding for this study. Please clarify.

 

DISCUSSION:

 

 

 

 

RESPONSE: 

 

 

Budget was unable to attend this meeting.  A teleconference was arranged on May 12, 2009 to address this agenda item.

 

 

 

 

 

 

 

 

 

 

 

 

 

3/09

 

                                  OCFS AGENCY LEVEL

PEF LABOR/MANAGEMENT

 

ISSUE:           Workplace Violence

 

NEW BUSINESS:                                                    NUMBER                 

 

OLD BUSINESS:                                                     NUMBER      _12___

 

COMMITTEE REPORTS:                                       NUMBER  ________

 

INFORMATION:                                                       NUMBER  ________

 

INITIATED BY:                                                          [X] LABOR  [   ]  MANAGEMENT

 

CONCERNS OF INITIATING PARTY:  PEF requests an update on the following:

1. Implementation of the Workplace Violence Legislation.

2. Update on progress of assessment (including who will be doing the office and facility assessments), policy, and training.

3. Number of staff injured in facilities for 2007 and 2008.

 

 

DISCUSSION:   

Management had expected the legislation to be done at this time. DOL regulations were to be out by 2/009. A teleconference for all employees was planned in April to announce the new legislation and what the agency is doing. Now it appears it will not be out until summer.  Cannot finalize a policy until the regulations are received.  The teleconference will be mandatory for all employees. A DVD will be provided to all facilities and program areas.

At the PEF Health & Safety Conference it was pointed out that OCFS was second only to OMRDD for Workers Comp claims at a rate of 14.3 per hundred.  Workers Comp claims increased from 385 in 2007 to 525 in 2008.

RESPONSE:    

 

Waiting for final regulations from DOL before Agency policy can be implemented.  Videoconference will be scheduled for training staff.

Assessment will be conducted by local Safety & Health Committees.

The Workplace Violence facility assessment tool will be piloted at Tryon Girls and Goshen facilities.

 

 

 

 

 

3/09

 

                      OCFS AGENCY LEVEL

PEF LABOR/MANAGEMENT

 

ISSUE:           Sub-Committee Reports             

 

NEW BUSINESS:                                                    NUMBER                 

 

OLD BUSINESS:                                                     NUMBER                      

 

COMMITTEE REPORTS:                                       NUMBER       1____

 

INFORMATION:                                                       NUMBER  ________

 

INITIATED BY:                                                          [X] LABOR [   ]  MANAGEMENT

 

CONCERNS OF INITIATING PARTY:  PEF requests the names of the Management representatives for each of the following committees.

 

Reports from the following sub-committees:

  1. Education: 

     Recently met and discussed teacher positions including substitutes.

          Concerned about reductions if Title 1 monies.                           

 

2.   Counseling:

           Committee is currently restructuring

 

3.   Alternative Work Schedule/ Telecommuting:

           This committee is formalizing its members

 

4.    Training and Staff Development: 

           Discussed Article 15 secure voucher program.

           STARS workplace initiative.

           Many programs are on GOER’s website.

           Monies are available for a variety of trainings.

 

5.   Nurses: 

Committee is currently restructuring. There have been two new members      added.

 

                     

                      

 

                      OCFS AGENCY LEVEL

PEF LABOR/MANAGEMENT

 

ISSUE:           Local Labor Management                                   

 

 

NEW BUSINESS:                                                    NUMBER                 

 

OLD BUSINESS:                                                     NUMBER                      

 

COMMITTEE REPORTS:                                       NUMBER                             

 

INFORMATION:                                                       NUMBER  ____1____

 

INITIATED BY:                                                          [X] LABOR [   ] MANAGEMENT

 

 

CONCERNS OF INITIATING PARTY: Report out from the last meeting regarding the updating of Local L/M committees.  PEF remains concerned that L/M meetings be held on a regular basis at all sites.

PEF requests an updated list of Management’s representatives at all sites.

 

DISCUSSION: 

 

 

 

 

 

 

RESPONSE:  

 

Still waiting for CSEA to send list for updates.

 

 

 

 

 

 

 

 

 

3/09

 

OCFS AGENCY LEVEL

PEF LABOR/MANAGEMENT

 

ISSUE:           Office Moves                       

 

NEW BUSINESS:                                                    NUMBER                 

 

OLD BUSINESS:                                                     NUMBER                      

 

COMMITTEE REPORTS:                                       NUMBER      ______          

 

INFORMATION:                                                       NUMBER  ____2___

 

INITIATED BY:                                                          [X] LABOR [   ]  MANAGEMENT

 

 

CONCERNS OF INITIATING PARTY:  PEF requests an update on moves and upcoming leases.

 

DISCUSSION: 

 

 

 

 

 

RESPONSE:    

 

155 lease expired.  DCC staff relocated to 3rd fl South Building at Capitol View. 

 

CBVH staff now at 2nd fl. 40 North Pearl st.

 

Child Welfare now at 2nd fl West Building at Capitol View

20 Exchange Street in NYC has been vacated.  Staff were moved to either the Harlem State Office Building or 80 Maiden Lane.

 

 

 

 

 

 

 

 

 

3/09

 

 

 

 

 

 

                        OCFS AGENCY LEVEL

PEF LABOR/MANAGEMENT

 

 

ISSUE:           Succession Planning                   

 

 

NEW BUSINESS:                                                    NUMBER                 

 

OLD BUSINESS:                                                     NUMBER      _             

 

COMMITTEE REPORTS:                                       NUMBER                 

 

INFORMATION                                                        NUMBER  ___3____

 

INITIATED BY:                                                          [X] LABOR [   ]  MANAGEMENT

 

CONCERNS OF INITIATING PARTY: PEF requests an update regarding activities being planned to prepare the workforce for the exodus of experienced staff.

 

 

DISCUSSION:

 

 

 

 

 

 

 

RESPONSE:   

 

Nothing new to report on this initiative.

 

 

 

 

 

 

3/09

 

                                        OCFS AGENCY LEVEL

PEF LABOR/MANAGEMENT

 

ISSUE:           Education Titles and Nurses Recruitment

 

 

NEW BUSINESS:                                                    NUMBER                 

 

OLD BUSINESS:                                                     NUMBER                      

 

COMMITTEE REPORTS:                                       NUMBER                 

 

INFORMATION:                                                       NUMBER ____4____

 

INITIATED BY:                                                          [X] LABOR  [   ]  MANAGEMENT

 

 

CONCERNS OF INITIATING PARTY:  PEF requests an update on the following:

1. Has the SCOPE conference been rescheduled with Civil Service regarding the disconnection between SED, Civil Service, and OCFS concerning Vocational titles?  If it has been rescheduled – when?  If it has not – what steps has the agency taken to push for rescheduling?

 

 

DISCUSSION:  

There is a process to bring in a vocational instructor with new certification.  It’s on a case by case basis.  There is a problem with becoming permanent without a test being offered.

 

 

 

RESPONSE:

 

B. Ruff has been following up with Civil Service. 

 

No SCOPE meeting has taken place.

 

No change in education titles with State Education.

 

 

 

 

3/09

 

 

 

 

 

 

                               OCFS AGENCY LEVEL

PEF LABOR/MANAGEMENT

 

ISSUE:           Communication/Technology/Cell Phones for RO Field Offices

 

 

NEW BUSINESS:                                                    NUMBER                 

 

OLD BUSINESS:                                                     NUMBER                      

 

COMMITTEE REPORTS:                                       NUMBER                 

 

INFORMATION:                                                       NUMBER ____5____

 

INITIATED BY:                                                          [X] LABOR  [   ]  MANAGEMENT

 

 

CONCERNS OF INITIATING PARTY:   PEF requests any updates regarding the tracking and use of cell phones in the Regional Offices.

 

DISCUSSION:

Cell phones are not an issue in some offices.  Management continues to monitor the situation.  Bill Dorr met with regional offices about this issue.  Any individual issues that arise around this topic should be brought to Bill’s attention and it will be dealt with..  OMS did distribute 20 more phones that only have 911 capability.

 

 

 

RESPONSE:

 

Regions are aware of the importance of staff having the ability to communicate when in the field.

 

Any problems or concerns should be directed to Bill Dorr in the Home Office.

 

 

 

 

3/09

 

 

               

               OCFS AGENCY LEVEL

PEF LABOR/MANAGEMENT

 

ISSUE:           Community Service Teams

 

 

NEW BUSINESS:                                                    NUMBER                 

 

OLD BUSINESS:                                                     NUMBER                      

 

COMMITTEE REPORTS:                                       NUMBER                 

 

INFORMATION:                                                       NUMBER ____6____

 

INITIATED BY:                                                          [X] LABOR  [   ]  MANAGEMENT

 

 

CONCERNS OF INITIATING PARTY:  PEF requests any updates regarding

 1. Case loads

 2. Status of positions that were previously approved but not yet secured.

 

 

DISCUSSION:

Queens/Long Island hired three new people.  Fifteen CMSO items were filled statewide.

 

 

 

RESPONSE:

 

PEF acknowledged some improvement in the downstate area with respect to staffing.

 

More items are coming, pending approval.

 

 

 

 

 

 3/09                            

      

                      

                     

       OCFS AGENCY LEVEL

PEF LABOR/MANAGEMENT

 

ISSUE:           Requests for Reasonable Accommodations

 

 

NEW BUSINESS:                                                    NUMBER                 

 

OLD BUSINESS:                                                     NUMBER                      

 

COMMITTEE REPORTS:                                       NUMBER                 

 

INFORMATION:                                                       NUMBER ____7____

 

INITIATED BY:                                                          [X] LABOR  [   ]  MANAGEMENT

 

 

CONCERNS OF INITIATING PARTY:  

1.    PEF requests any updates, pending review of the policy that was recently forwarded to PEF.

2.    Update and status of any RA’s requested in the last six months.

 

 

 

DISCUSSION:

Policy was sent to PEF.  PEF made recommendations and returned it to management.  It is currently in the review process and will be sent back to PEF.

 

 

 

 

 

RESPONSE:

 

EODD reported this policy is currently in the review process.

 

Ray will get data and send to J. Ludwig.

 

 

 

 

 3/09                                 

 

                        

      OCFS AGENCY LEVEL

PEF LABOR/MANAGEMENT

 

ISSUE:           Agency Labor/Management

 

 

NEW BUSINESS:                                                    NUMBER                 

 

OLD BUSINESS:                                                     NUMBER                      

 

COMMITTEE REPORTS:                                       NUMBER                 

 

INFORMATION:                                                       NUMBER ____8____

 

INITIATED BY:                                                          [X] LABOR  [   ]  MANAGEMENT

 

 

CONCERNS OF INITIATING PARTY:  

PEF requests discussion regarding joint training initiative at the Agency level, including the status of the assessment form that was provided to Management.

 

DISCUSSION:

 

 

 

 

 

 

 

 

RESPONSE:

 

This initiative is on-going.  Management provided this assessment form.

 

 

 

 

 

 

 

 

3/09

 

                             

 

                               OCFS AGENCY LEVEL

PEF LABOR/MANAGEMENT

 

ISSUE:           Facility Capacity Reports

 

 

NEW BUSINESS:                                                    NUMBER                 

 

OLD BUSINESS:                                                     NUMBER                      

 

COMMITTEE REPORTS:                                       NUMBER                 

 

INFORMATION:                                                       NUMBER ____9____

 

INITIATED BY:                                                          [X] LABOR  [   ]  MANAGEMENT

 

 

CONCERNS OF INITIATING PARTY:  PEF requests copies of the Monday Morning Capacity reports, by facility, for the last 3 months.

 

DISCUSSION:

 

Clarification was requested regarding what  information was being requested.  DJJOY responded that there is more than one report that indicates capacity.

 

 

 

 

RESPONSE:

Reports will be provided for the last three months.

 

 

 

 

 

 

 

 

 